DIASPAR WP3 timeline

Timeline for the project
Author

Briand Cédric, Oliviero Jules, Helminen Jani

Published

04-04-2025

Habitat DB

The habitat DB also corresponds to some of the dictionaries created for the stock DB.

More details here :

github timeline

issues

main report

gantt
    title Habitat database project timeline
    dateFormat  YYYY-MM-DD
    axisFormat  %m
    todayMarker stroke-width:5px,stroke:#0f0,opacity:0.5


    section Build river referentials



    section Needs / format
    start   :milestone, start, 2024-06-01, 0d
    Needs of ICES expert working groups #8 :done, 2024-06-01, until init
    Discuss interoperability and storage with ICES and GFM #9 :done, 2024-11-01, until init
    Initial meeting   :milestone, init, 2024-11-25, 3d
    Analyse spatial structure :done, 2024-12-01, 5w
    WP2 Analysis of eel data :active, after init, until v1
    section GIS DB
 
    Get all data from different species  #6 :done, 2024-09-01, 7M
    Populate the DB using Hydro Atlas data  #7 :done, 2024-09-01, 7M
    Populate DB using EU hydro #26 :active, 2025-02-01, 6M 
    Export format Arrow & postgres #11 :active, 2025-02-01, until alpha
    Beta release (basins)   :milestone, beta, 2025-03-15, 3d
    Alpha release (hierarchy WGBAST)   :milestone, alpha, 2025-06-15, 3d
    v 0.0.1 (rivers hierarchy WGNAS)   :milestone, v1, 2025-09-15, 3d
    v 0.0.2 (eel)   :milestone, v2, 2026-03-01, 0d


    section Validation
    WGNAS habitat #22 :active, after alpha, until final
    WGBAST habitat #21 :active, after alpha, until final
    Validation meeting: milestone, valid, 2025-10-15, 3d
    Final meeting   :milestone, final, 2025-12-01, 0d
    WGEEL habitat #23 :active, after v1, until v2
    Release to ICES: active, after v2, until end

    End projet   :milestone, end, 2026-06-01, 0d

Stock DB

This is the main database where we wish to put all unified data, details on the data structure coming out but still need validation from ICES.

More details here :

github timeline

issues

main report

    gantt
    title Stock DB Timeline
    dateFormat  YYYY-MM-DD
    todayMarker stroke-width:5px,stroke:#0f0,opacity:0.5

    section Collect data and needs
    Needs of ICES expert working groups #8 :done, 2024-06-01, until init
    Link with RDBES/ICES/GFCM :done, 2024-08-12, until init
    Initial meeting:milestone, init, 2024-11-25, 3d
    Collect DB from WGNAS :done, 2024-06-01, 2024-08-30
    Collect DB  From WGBAST :done, 2024-11-01, 2025-01-01

    section Buid DB
    WGNAS WGBFAS and WGTRUTTA database description : done, after init, until 2024-03-01
    Create template DB :crit, 2024-12-30, until beta


    section Import
    Import data from WGNAS :current, 2025-02-01, until beta
    Beta version (WGNAS): milestone, beta, 2025-06-01, 2d
    Import data from WGEEL : after beta, until alpha
    Alpha version (WGEEL): milestone, alpha, 2025-07-15, 2d
    Import data from WGBAST landings: current, after alpha, until v1
    V0.0.1 (WGBAST landings): milestone, v1, 2025-10-15, 2d
    Import data from WGBAST young fish : after v1, until v2
    V0.0.2 (WGBAST young fish): milestone, v2, 2025-11-15, 2d
    Import data from WGBAST (stock) : after v2, until end

    section validate

    Database structure with ICES: crit, after alpha, 1M
    Release first vocab to ICES: current, after alpha, 1M
    Validate structure with WGNAS: after alpha, until final
    Validate structure with WGEEL: after alpha, until final
    Validate structure with WGBAST: after alpha, until end
    Validate structure with WGTRUTTA: after alpha, until end
    Validation meeting: milestone, valid, 2025-10-15, 3d
    Final meeting:milestone, final, 2025-12-01, 3d
    ICES Import to ICES db: crit, after final, until v3

    section shiny / R

    Export nimble functions WGNAS: current, after final, 2026-02-01

    V0.0.3 (WGBAST model): milestone, v3, 2026-04-01, 2d
    Propose and adapt changes to shiny apps : current, after v3, until end
    WP3 DELIVERABLE (template database) : milestone, end, 2026-06-01,3d

Metrics DB

This database is part of the previous DB, using the same vocab, but the data structure is different. There is already a mapping by ICES of the data structure. The DB is currently in WGEEL (series + sampling) and we’ve release excel sheets to call for LHT with WP2.

gantt
    title Metrics timeline
    dateFormat  YYYY-MM-DD
    todayMarker stroke-width:5px,stroke:#0f0,opacity:0.5

    section Collect data and needs
    Initial meeting:milestone, init, 2024-11-25, 3d


    section Buid DB
    Beta version vocab (stockDB): milestone, betastock, 2025-06-01, 2d
    Write simplied structure using WGEEL :crit, after betastock, until beta
    Beta version (Metrics): milestone, beta, 2025-08-01, 2d


    section Import

    Import data WGEEL : after beta, until alpha
    Alpha version (Metrics): milestone, alpha, 2025-11-15, 2d
    Final meeting:milestone, final, 2025-12-01, 3d
    Import data WP2  : current, 2026-01-01, until end

    

    section validate

    Database structure with ICES: crit, after alpha, 1M
    Validate structure with WGNAS: after alpha, until end
    Validate structure with WGEEL: after alpha, until end
    Validate structure with WGBAST: after alpha, until end
    Validate structure with WGTRUTTA: after alpha, until end

    ICES Import to ICES db: crit, after final, until end

    section shiny / R

    WP3 DELIVERABLE (template database) : milestone, end, 2026-06-01,3d
    Propose and adapt changes to shiny apps ... : crit, 2026-03-01, 6M
    Create datacall WGEEL ... : crit, after end, 3M

 

EU is not reponsible for the content of the project